Current Projects >> Kerepehi Water Treatment Plant Upgrade

Kerepehi Water Treatment Plant Upgrade

Marra are currently working on the upgrade of the existing Water Treatment Plant at Kerepehi. The current upgrade is being undertaken to increase the WTP throughput capacity to 12,500m³/day.

This contract includes installation of flash mixer, flocculation towers, retrofitted clarifiers, membrane balance tank, membrane plant building, UV disinfection system, chemical dosing, sludge system and new electrical equipment and control system.

Estimated completion of this $1.5 million dollar contract is June 2012.

Quantity Surveyor/Project Manager: Neill Marra

Site Manager: Nick Thompson

 

 

 

 

 